Study and technical assistance for the rehabilitation of the community road CU9: KOUPELA - TENKODOGO-BITTOU-CINKANSE - TOGO border and the MOGANDE-LOT ramp N ° 3
AFRICA ENGINEERING
Study and technical assistance for the rehabilitation of the community road CU9: KOUPELA - TENKODOGO-BITTOU-CINKANSE - TOGO border and the MOGANDE-LOT ramp N ° 3
COUNTRY
Burkina Faso
CUSTOMER
SOROUBAT
STARTING DATE
2014
COMPLETION DATE
2016
Project description
The project concerns the construction of the PK 76 + 000 section at PK 149 + 328 (Togo border) including construction and asphalting of the Mogandé ramp (3.34 km)
Description of services
Studies Technical implementation.
Preparation of implementation plans Preparation of the hydrological and hydraulic verification note.
Preparation of the sizing note for the pavement.
Establishment of plans for the execution of transverse structures, hydraulic and drainage works.
Preparation of fronts, calculation notes, justification.
Preparation of horizontal and vertical signaling planes and equipment.